Highland publishes the yes-and-no list
Most cities make you call to learn whether a small job needs a permit. Highland prints it. Basement finishes: required. Painting: not required. Replacing plumbing fixtures: not required. Electrical, mechanical and plumbing work: required. Installation or replacement of windows and doors is on the sheet as well, so a like-for-like interior door in Highland is a question for the Building Division rather than an assumption. The FAQ's structural test is the tiebreaker for anything not named: if a floor, wall, roof, window or door is added, removed or changed, it needs a permit. That is the same line that separates a Utah R101 finishing contractor from a general contractor, and it is why we quote the finish and refer the opening.
$45 to start, then valuation
Highland's Basement Finish Submittal packet asks for a $45 non-refundable plan-review fee at submittal, and the city's FAQ lists a $45 deposit for sheds, garages, remodels, additions and basements. The permit fee itself is then set from construction valuation, with Utah's 1 percent state fee on top. There is no flat basement-finish total, and the total for a given square footage is the Building Division's to state; the written scope lists it at cost.
The inspection ladder, and the rungs a basement uses
Highland publishes its full residential inspection sequence, twelve steps from footings to final: footings, foundations, temporary power, underground plumbing, the four-way covering electrical, plumbing, mechanical and framing, permanent power, stucco, weather barrier, flashing, sheetrock, shower pan, and the final inspection. A basement finish inside an existing house uses the middle of that ladder. The four-way after framing and rough-ins, sheetrock before tape, the shower pan if the plan includes a tiled shower, and the final. Inspections are Monday through Thursday with the office open 8 to 5, and Friday inspections by appointment, so a stage finished on a Friday afternoon waits until the following week.
Which code edition Highland means
This is the one place Highland's documents disagree with each other. The Building Division page lists, as of July 1, 2026, the 2021 IRC, the 2023 NEC and the 2024 IBC among the codes in force. The basement-finish packet still says plans must meet the 2021 IRC as amended by the State of Utah. For a basement finish those two statements agree on the residential code, which is the one that governs ceiling height, egress and alarms. We build to the packet's 2021 IRC as amended, and our electrician designs to the 2023 NEC the page lists; where a plan touches the difference, we ask the Building Official rather than reconcile the two documents ourselves.
The portal, and the semi-rural lot
Highland runs permits through a cityinspect portal that requires a registration before the first application. Highland's lots are larger and more rural than the rest of our service area, and a share of its homes were built in phases by their owners, which means the lower level often has a mix of finished and unfinished areas and an older four-way behind some of the walls. We photograph what is behind any wall we open and put it in the scope, because the city will ask what was there before.
Who files it when we do the work
On a Highland finish we register and submit through the portal under our Utah R101 license, pay the $45 review fee at cost, book each rung of the ladder as the stage is ready, and write it all on the quote. Electrical and plumbing rough-ins go to licensed trades with their own permits.
Bottom line
Highland prints the list, takes $45 to open the file, and runs a twelve-rung inspection ladder of which a basement uses four. Build to the packet's 2021 IRC, register on the portal first, and finish stages before Friday.
Questions
Do I need a permit to paint a finished basement room in Highland?
No. Highland's When Do I Need a Building Permit sheet lists painting as work that does not require a permit. Finishing unfinished space into living space is listed as required.
What is the fee for a Highland basement finish permit?
A $45 non-refundable plan-review fee at submittal, then a permit fee set from construction valuation plus Utah's 1 percent state fee. The Building Division at 801-772-4516 states the total for your square footage.
When can inspections happen in Highland?
Monday through Thursday during the Building Division's 8 to 5 hours, with Friday inspections by appointment, per the city's pages.